Phase 1 reached the second-floor concrete pour, masonry works continued across phases 1 and 2, and mechanical-services installation began in phase 2.
MEDAR PORT · CONSTRUCTION DIARY
Progress on site,
month by month.
March — October 2026
Real records
from the site.
Dated site photographs document key construction milestones in MEDAR PORT phases 1 and 2. The latest records appear first.
This diary presents selected site records. Not every completed operation was photographed individually; the images document the main visible stages of construction.
Reinforcement, formwork and concrete placement continued as the buildings gained additional floors.
Floor, column, shear-wall and formwork operations progressed at different levels across the two phases.
Floor construction continued and formwork materials were moved around the site.
Reinforced-concrete structural and floor works continued in phases 1 and 2.
Waterproofing, foundation infrastructure and reinforced-concrete floor works continued in parallel.
After foundation reinforcement and service preparation in phase 2, work advanced to foundation concrete and basement construction.
Excavation and lean-concrete work began across phases 1 and 2 while the sales office was set up.
FOLLOWING PHASES
Phases 3, 4 and 5
- Status
- Project-planning stage
- Planned start
- January 2027
- Planned completion
- December 2028
Contact TEYRA directly for the latest construction progress and project schedule.