MEDAR PORT · CONSTRUCTION DIARY

Progress on site,
month by month.

March — October 2026

Real records
from the site.

Dated site photographs document key construction milestones in MEDAR PORT phases 1 and 2. The latest records appear first.

This diary presents selected site records. Not every completed operation was photographed individually; the images document the main visible stages of construction.

Phases 1 and 2
Construction in progressPlanned delivery · 31 March 2027Last documented update · October 2026

Phase 1 reached the second-floor concrete pour, masonry works continued across phases 1 and 2, and mechanical-services installation began in phase 2.

Reinforcement, formwork and concrete placement continued as the buildings gained additional floors.

Floor, column, shear-wall and formwork operations progressed at different levels across the two phases.

Floor construction continued and formwork materials were moved around the site.

Reinforced-concrete structural and floor works continued in phases 1 and 2.

Waterproofing, foundation infrastructure and reinforced-concrete floor works continued in parallel.

After foundation reinforcement and service preparation in phase 2, work advanced to foundation concrete and basement construction.

Excavation and lean-concrete work began across phases 1 and 2 while the sales office was set up.

FOLLOWING PHASES

Phases 3, 4 and 5

Status
Project-planning stage
Planned start
January 2027
Planned completion
December 2028

Contact TEYRA directly for the latest construction progress and project schedule.